The painting project of Jam Petrochemical Olefin Unit was assigned to Jam Sanatkaran Company

The executive operation of the painting project of the olefin unit of the Jam Petrochemical Complex in sections such as lines, equipment, metal structures, as well as the numbering of the lines has started on December 03, 2021 According to the public relations report of Jam Sanatkaran Company, the implementation of the painting project of […]
53% progress of the installation and commissioning of the permanent butadiene loading system project at the Takht Jamshid Petrochemical Company – Bandar Mahshahr

In its report, Jam Sanatkaran Company announced the progress of 53% of the installation and commissioning of the permanent butadiene loading system project in Persepolis Petrochemical. According to the public relations report of Jam Sanatkaran Company, the operation of construction, installation and commissioning of permanent butadiene ½ loading system of Takht Jamshid Petrochemical Company started […]
Completing the contracting services of Jam Sanatkaran restaurant building and operating it in the near future

The manager of the restaurant building contracting project of Jam Sanatkaran Company announced the completion of the main executive activities and operation of the project in the near future. According to the public relations report of Jam Sanatkaran Company, Mr. Amin Masoudi, referring to the objectives of the restaurant building contracting project, said: “The restaurant […]
Jam Sanatkaran Company succeeded in obtaining a contractor safety qualification certificate from the Ministry of Labor

With another success in the field of providing industrial contracting services, Jam Sanatkaran Industrial Company succeeded in obtaining a contractor safety qualification certificate from the Ministry of Labor. According to the public relations report of jam Sanatkaran Company, this company, as one of the leading companies in the field of providing industrial contracting services, succeeded […]
10 progress of the project of replacing cooling water lines from GRP to carbon steel in Jam Petrochemical – Asalouye%

The technical vice-president of Jam Sanatkaran Company announced the progress of Jam Petrochemical cooling water line replacement project in his November report. Jam Santeakaran Company has put the follow-up of all executive operations and the progress of the project of replacing the cooling water lines from GRP to carbon steel with high priority. In the […]
Successful implementation of Marjan Petrochemical parts and goods warehouse arrangement project by Jam Sanatkaran Company

Jam Sanatkaran Company completed the first phase of the Marjan petrochemical parts and goods storage project within 8 months and according to the schedule. The head of project planning and control of Jamsanatkaran Company announced the successful implementation of the Marjan Petrochemical Parts and Goods Warehouse layout project in two phases by the team of […]