The construction and development project of Jam Petrochemical Central Restaurant – Asalouye

Information on the construction and development project of Jam Petrochemical Central Restaurant

Additional details of the construction project of the central petrochemical restaurant of Jam

According to the announcement of Mr. Messhenas , the construction and development project of Jam Petrochemical Central Restaurant started after moving the machinery unit to its new location at the end of March 2019. The construction project of Jam Petrochemical Central Restaurant was prepared for the preparation of the substrate and the implementation of concrete after the excavation and concrete demolition. The construction and development project of Jam Petrochemical Central Restaurant is now in the reinforcement stage for the implementation of the foundation.

The infrastructure of the whole construction and development plan of the restaurant, corridors and new cold rooms is about 2,600 square meters on the ground floor and 600 square meters on the first floor in the form of a VIP hall with related terraces.

The construction and development project of Jam Petrochemical Central Restaurant makes it possible for all the forces working in Jam Petrochemical Complex to use the restaurant building at the same time after the end of the restrictions related to the Covid-19 disease.

Jam Sanatkaran Company has previously been responsible for the implementation of all construction projects of Jam Petrochemical Industrial Units.

The purpose of the construction project of the central petrochemical restaurant of Jam

The construction and development project of Jam Petrochemical Central Restaurant with an area of approximately 3,200 square meters is underway to provide optimal service to the employees of this industrial unit.

The type of industrial structure and the workload of the restaurant building project

  • Area of the restaurant building (ground floor and first floor total): 3,200 square meters
  • Industrial structure system: bending frame (Moment Frame Structure)
  • Roof system: Steel Deck
  • Excavation operation: 1,400 cubic meters
  • Reinforcement operation: 75,000 kg
  • Molding operation: 1,500 square meters
  • Concrete pouring operation: 900 cubic meters
  • Restaurant capacity (ground floor and first floor total): 1,400 people

Features and strengths of the construction and development project of Jam Petrochemical Central Restaurant

  • Carrying out explosion risk studies and applying special considerations in the design of the restaurant construction project due to its proximity to Jam Petrochemical Unit B1
  • Optimum financing of the project and implementation of the optimal supply chain
  • Carrying out executive operations without disrupting the traffic of vehicles and serving the kitchen of the central Petrochemical Jam restaurant
  • Focusing on obtaining and applying the technical opinions of all stakeholders in the implementation of the construction and development plan of the central restaurant of Jam Petrochemical
  • Using and applying efficient principles and standards in managing the industrial project of restaurant construction and development

The services provided in the construction project of Jam Petrochemical Restaurant building

  • Design and implementation of restaurant construction

  • Supply of industrial equipment and materials for restaurant construction and development

  • Providing human resources for the restaurant construction and development project